Delay expected for Tuy-Dasmariñas transmission project — NGCP

by
May 16, 2024
in Stock
0
Delay expected for Tuy-Dasmariñas transmission project — NGCP

THE National Grid Corp. of the Philippines (NGCP) said the completion of the Tuy-Dasmariñas 230/500-kilovolt (kV) transmission line and substation project may be delayed after a regional court ordered relocation of two tower sites.

“The tower parts for the current route have already been manufactured, and it is unlikely that a revised route will make use of the same tower type. We will have to manufacture tower parts from scratch,” the grid operator said in a statement on Thursday.

There would also be an additional construction and right-of-way costs that could be incurred, it said.

The NGCP said that it filed expropriation cases against E.M. Ramos and Sons, Inc. and several other defendants who claim interest over the properties affected by 15 of the 135 towers to be constructed for the project.

The regional trial court of Dasmariñas has issued writs of possession (WoP) for both cases.

However, in an order dated April 8, the regional court ruled to reinstate the previously withdrawn WoP but confirmed the previous order to relocate two towers.

The NGCP said that the expropriation-related delays may lead to additional costs, as well as potential power interruptions as it may hamper the entry of an additional 5,21.55 megawatts in proposed generation capacity near Calaca, Batangas.

The completion of the transmission project is targeted for December of this year.

However, the project could be delayed by an estimated 27 months, involving about a year for right-of-way acquisition and roughly 15 months more for survey, procurement, fabrication of materials, and construction.

“We will be pursuing all remedies available to us to expedite the resolution of the issue. Our priority is to finish our projects on time and prevent avoidable delays of this kind,” the NGCP said.

“We ask our stakeholders to recognize that delays in our projects impact the public directly,” it added.

The Tuy-Dasmariñas 230 kV transmission line project was approved by the Energy Regulatory Commission with an approved cost of P3.05 billion.

The Tuy 500-kV Substation Project Stage 1, with an applied cost of P8.454 billion, is still awaiting ERC approval. — Sheldeen Joy Talavera

Previous Post

Megaworld board OK’s Alliance Global share subscription

Next Post

Getting up close and personal via VR

Next Post
Getting up close and personal via VR

Getting up close and personal via VR

Enter Your Information Below To Receive Free Trading Ideas, Latest News And Articles.







    Fill Out & Get More Relevant News





    Stay ahead of the market and unlock exclusive trading insights & timely news. We value your privacy - your information is secure, and you can unsubscribe anytime. Gain an edge with hand-picked trading opportunities, stay informed with market-moving updates, and learn from expert tips & strategies.
    Your information is secure and your privacy is protected. By opting in you agree to receive emails from us. Remember that you can opt-out any time, we hate spam too!

    Recommended

    One in six UK workers struggling to pay bills as second jobs hit record high

    One in six UK workers struggling to pay bills as second jobs hit record high

    July 12, 2025
    JuanHand earns Green Flag recognition from Filipino Fair Loans Advocacy Group (FILFLAG)

    JuanHand earns Green Flag recognition from Filipino Fair Loans Advocacy Group (FILFLAG)

    July 11, 2025
    United under one roof: How Puregold brought generations of OPM together in the Philippine Arena

    United under one roof: How Puregold brought generations of OPM together in the Philippine Arena

    July 11, 2025
    UK government considers rescue deal for Speciality Steel amid fears of collapse

    UK government considers rescue deal for Speciality Steel amid fears of collapse

    July 11, 2025

    Disclaimer: 5GInvestmentNews.com, its managers, its employees, and assigns (collectively “The Company”) do not make any guarantee or warranty about what is advertised above. Information provided by this website is for research purposes only and should not be considered as personalized financial advice.
    The Company is not affiliated with, nor does it receive compensation from, any specific security. The Company is not registered or licensed by any governing body in any jurisdiction to give investing advice or provide investment recommendation. Any investments recommended here should be taken into consideration only after consulting with your investment advisor and after reviewing the prospectus or financial statements of the company.

    • Privacy Policy
    • Terms & Conditions

    Copyright © 2024 5GInvestmentNews. All Rights Reserved.

    No Result
    View All Result
    • Home
    • Privacy Policy
    • suspicious engagement
    • Terms & Conditions
    • Thank you

    © 2025 JNews - Premium WordPress news & magazine theme by Jegtheme.